Does the assessment of a compensation event include an allowance for risk?

Does the assessment of a compensation event include an allowance for risk?

Assessment of the effect of a compensation event includes risk allowances for cost and time for matters which have a significant chance of occurring and are at the Contractor’s risk under this contract (see clause 63.6)