Does information in the Bill of Quantities count as Works Information or Site Information?
No. Information in the Bill of Quantities is not Works Information or Site Information (see Clause 55.1).
Does information in the Bill of Quantities count as Works Information or Site Information?
No. Information in the Bill of Quantities is not Works Information or Site Information (see Clause 55.1).