I am working on a contract that has staff rates in CDP2. We’ve incurred significant delay caused by the Client.
We don’t have X1 in our contract but have tried to apply BCIS to the staff rates to account for the inflation we have suffered due to the project being extended out considerably.
The Client is pushing back saying we need to stick to the contract rates and not apply BCIS. Is there any way to recover the inflation we have had when there is no X1 in the contract as we were not at fault for the delays?