Charges - Cll 44 Surveying and Setting Out Equipment

Clause 44 (h) of the Schedule of Cost Components includes for the provision and use of surveying and setting out equipment as included within the Working Area Overhead (WAO).

Can you advise if the charge includes provision and use of the following equipment:

Cat and Genny
Total Station
Rotating Laser Level
Tripod

Regards

Joseph

They all seem to fall under the heading of surveying & setting out Equipment so ‘Yes’.