What can the Project Manager do if a Defect is found which is due to a fault in the Employer’s design?

What can the Project Manager do if a Defect is found which is due to a fault in the Employer’s design?

1 Like

The Project Manager may decide to change the design and instruct the Contractor accordingly. This would constitute a change to the Works Information, which would be a further compensation event under Clause 60.1(1) in addition to the compensation event which has already occurred under Clause 60.1(10).