Can the Project Manager accept or reject the Contractor’s proposals for improving performance?

Can the Project Manager accept or reject the Contractor’s proposals for improving performance?

The Project Manager can neither accept nor reject the Contractor’s proposals since he cannot coerce the Contractor into achieving a target.