NEC: Which CE would delays due to Coronavirus be?
|
|
4
|
3278
|
31 March 2020
|
NEC ECC: Period for design acceptance
|
|
1
|
1053
|
27 March 2020
|
NEC ECC: Accepted Programme with un-agreed CE duration's within it
|
|
3
|
1603
|
27 March 2020
|
NEC ECC: Accepted programme
|
|
3
|
878
|
27 March 2020
|
NEC ECC: Acceptance of Programme and Delay in Progress Onsite
|
|
1
|
743
|
14 March 2020
|
NEC ECC: Acceleration quotation
|
|
3
|
855
|
9 March 2020
|
NEC ECC: Cl.31.2 - provisions for float........can it be positive, negative and neutral?
|
|
2
|
1138
|
17 February 2020
|
NEC ECC: Can a Contractor claim loss of bonus/incentive payment/profit if a Subcontractor misses a Key Date?
|
|
2
|
446
|
13 February 2020
|
NEC ECC: Timing of Instructions that have potential impacts
|
|
3
|
482
|
11 February 2020
|
NEC ECC: Missing item in Accepted Programme
|
|
1
|
682
|
11 February 2020
|
NEC ECC: No work on programme
|
|
1
|
411
|
9 February 2020
|
NEC ECC: Acceleration and delay damage entitlement
|
|
1
|
580
|
7 February 2020
|
NEC ECC: Monthly programme displaying delay but no CE
|
|
2
|
990
|
28 January 2020
|
NEC ECC: Access Dates and accessing site prior to this date?
|
|
1
|
1033
|
23 January 2020
|
NEC ECC: Lack of Employer access under option A on the programme being a CE?
|
|
1
|
708
|
23 January 2020
|
NEC ECC: is there an extension of time if there are weather related issues?
|
|
1
|
568
|
13 January 2020
|
NEC ECC: Programme update instruction
|
|
2
|
527
|
11 December 2019
|
NEC ECC: Switch date for assessing time in a compensation event
|
|
1
|
888
|
27 November 2019
|
NEC ECS: If I accept a subcontrcator's programme that is late do I therefore extend his Completion Date
|
|
1
|
681
|
14 November 2019
|
NEC ECC: Target Programme vs Contract Programme
|
|
2
|
1265
|
12 November 2019
|
NEC ECC: Clause 32.2 submitting programme on PM instruction
|
|
2
|
1205
|
10 October 2019
|
NEC ECC: Must the Sectional Completion Date (X5) be moved if the Condition for a Key Date relevant to that section is later than the Sectional Completion Date?
|
|
1
|
876
|
7 October 2019
|
NEC ECC: Clause 34.1 stop any work
|
|
1
|
772
|
28 August 2019
|
Employer instructed inclusion of TRA
|
|
1
|
575
|
16 August 2019
|
NEC ECC: Under the NEC what does "Access Date" mean
|
|
3
|
2901
|
15 August 2019
|
NEC4 ECC - X22 Proposals for Stage 2
|
|
1
|
555
|
6 August 2019
|
NEC ECC: Assessing CE delays against our own delays
|
|
1
|
629
|
6 August 2019
|
NEC ECC: Programme and time risk allowance
|
|
2
|
943
|
30 July 2019
|
NEC ECC: Resource levels and impact of delay on programme
|
|
2
|
700
|
30 July 2019
|
NEC ECC: Contract Date
|
|
1
|
684
|
29 July 2019
|