NEC3 ECC: Is travel time between Working Areas recoverable under ECC Option C?
|
|
1
|
1153
|
5 April 2017
|
NEC3 ECC: Schedule of cost components - people outside the Working Areas
|
|
1
|
3810
|
24 March 2017
|
NEC3 ECC: Cost of Insurance Policy which is non compliant to the contract is disallowed?
|
|
1
|
643
|
16 January 2017
|
Loss of Opportunity Claim
|
|
1
|
969
|
20 December 2016
|
NEC3 ECC: Is defined cost a cost excluding mark-up?
|
|
2
|
1084
|
24 November 2016
|
NEC3 ECC: T&S costs relative to the SCC
|
|
3
|
888
|
7 November 2016
|
NEC3 ECC: Contract Manager or Director costs
|
|
1
|
1135
|
18 October 2016
|
Using both SCC and SSCC under ECC Main Option A & C?
|
|
1
|
782
|
25 August 2016
|
NEC3 ECC: Could some one please explain to me what the "on cost charge" as referenced in item 23 in the Schedule of Cost Components
|
|
1
|
754
|
7 August 2016
|
NEC3: Option D; In Schedule of Cost Components (SoCC) 1.2 & 1.3, Is it a requisite that these items should be included as entitlements in the Employment Contract or HR policies?
|
|
1
|
406
|
7 August 2016
|
NEC3: Option D; In Schedule of Cost Components (SoCC) 1.2 & 1.3, Is it a requisite that these items should be included as entitlements in the Employment Contract or HR policies?
|
|
2
|
440
|
22 July 2016
|
NEC3 ECC: People in the working area
|
|
2
|
977
|
10 June 2016
|
NEC3 ECC: Plant Operator Costs under the SOCC
|
|
1
|
960
|
3 June 2016
|
NEC3 ECC: Percentage of People Overheads applied to Subcontractor's People
|
|
2
|
5257
|
27 May 2016
|
NEC3 ECC: Temporary fencing to the Site
|
|
2
|
951
|
18 May 2016
|
NEC3 ECC: Payments for People in Working Areas
|
|
2
|
2701
|
16 May 2016
|
NEC3 ECC: Sett off costs for hired plant failures
|
|
1
|
600
|
9 May 2016
|
NEC3 Use of rates for Defined Cost
|
|
1
|
986
|
30 April 2016
|
ECC NEC3: Option A - Do self-employed/agency staff, in CE Assessments, have the people overhead and fee applied OR the sub-contract fee only?
|
|
1
|
609
|
21 March 2016
|
NEC3 ECC: Can the Working Areas overhead percentage be subject to change if the Contractor's intended delivery changes from subcontracted to direct delivery?
|
|
2
|
931
|
18 March 2016
|
NEC3 ECC: Professional fees included in SCC?
|
|
1
|
1223
|
12 February 2016
|
NEC3 ECC: Long term sickness on an option C
|
|
1
|
888
|
11 February 2016
|
NEC3: How can I forecast defined cost of a compenation event if rates are not included in SSCC?
|
|
1
|
2665
|
19 January 2016
|
NEC: ECC Option A - how do I assess Compensation Events when the Shorter Schedule of Cost Components does not include rates for People?
|
|
1
|
4025
|
16 January 2016
|
NEC3 ECC: Under the SSCC (option C) are lunch breaks payable at the rates
|
|
1
|
1001
|
11 December 2015
|
NEC3 ECC SOCC Treatment of companies within the same group of companies
|
|
4
|
819
|
1 December 2015
|
NEC3 SOCC - Cost of Travel to and from the Working Areas
|
|
1
|
852
|
27 November 2015
|
NEC3 ECC Option C - sick pay, maternity pay or redundancy paid at cost incurred or at the statutory minimum
|
|
1
|
1583
|
27 November 2015
|
NEC3 SOCC - Is the cost of the time incurred in travelling to the Working Areas allowable
|
|
1
|
796
|
27 November 2015
|
NEC3 ECC: Are vans classed as Equipment under the SOCC
|
|
2
|
1013
|
10 November 2015
|