|
NEC ECC: (Option C) - In accordance with the SOCC would a 'taxable site based travel allowance' be classified as 13 (b) 'subsistence and lodging'?
|
|
1
|
1068
|
6 March 2019
|
|
NEC ECC: Can you have different fee percentages for different costs
|
|
1
|
585
|
6 February 2019
|
|
NEC ECS: Deduction for breaks?
|
|
1
|
1288
|
5 February 2019
|
|
NEC ECS: When does incidental works become non-incidental?
|
|
2
|
1194
|
3 February 2019
|
|
NEC ECC: Option C - Disallowed Costs
|
|
1
|
1076
|
16 January 2019
|
|
NEC ECC: WAO on Cost of People within a Subcontract
|
|
3
|
889
|
11 January 2019
|
|
NEC ECC: Under an Option C contract, does the defined cost of "Equipment" include costs associated with repair and maintenance?
|
|
1
|
1816
|
10 January 2019
|
|
NECECC: Is the provision of a company car, including a fully expensed fuel card allowed under defined cost for an Option C?
|
|
3
|
1719
|
18 December 2018
|
|
NEC ECC: Option A - People Overheads
|
|
1
|
914
|
23 November 2018
|
|
NEC ECC: SCC- Item 44
|
|
4
|
1436
|
25 October 2018
|
|
NEC3 ECC : Should the Project Completion Bonus be paid as part of Defined Cost
|
|
2
|
749
|
10 October 2018
|
|
NEC ECS: Is travel time payable under option A?
|
|
1
|
813
|
25 September 2018
|
|
NEC ECC: Working Area Overhead Percentage and Agreed Subcontract Rates
|
|
1
|
3383
|
26 August 2018
|
|
NEC ECS: What is the definition of a Subsubcontractor under NEC3?
|
|
3
|
1282
|
10 July 2018
|
|
NEC ECC: Option C - removal of items 12/13 of SCC
|
|
1
|
601
|
7 June 2018
|
|
NEC ECC: What about maternity pay and also paternity pay?
|
|
3
|
1292
|
6 June 2018
|
|
NEC ECC: Option C Schedule of Cost Components - People under NEC3
|
|
3
|
2022
|
15 May 2018
|
|
NEC ECC: Contract Data & SSCC
|
|
3
|
1140
|
14 May 2018
|
|
NEC ECC: Recovering Laundry costs under The Shorter Schedule Of Cost Components
|
|
2
|
536
|
22 March 2018
|
|
NEC ECC: CECA applied for weekend work when hire cost covered in weekday working?
|
|
1
|
632
|
7 March 2018
|
|
NEC3 ECC: Option B SSoCC Payments for Electricity
|
|
1
|
584
|
2 March 2018
|
|
NEC ECC: No working area in SSCC?
|
|
1
|
875
|
1 January 2018
|
|
NEC3 ECC: Does Defined Cost include the WAOH %
|
|
3
|
823
|
10 November 2017
|
|
NEC ECC: What about if the Contractor Employs a person who must travel to site, his only working site
|
|
1
|
669
|
9 November 2017
|
|
NEC3 ECC Option C: Does WAO apply to Agency Supplied Workers?
|
|
3
|
1838
|
3 November 2017
|
|
NEC ECC: apprenticeship levy a Compensation Event
|
|
3
|
813
|
16 October 2017
|
|
NEC3 ECC: Option E Fee on Fee
|
|
1
|
2596
|
11 October 2017
|
|
NEC ECC: What is the difference between Socc 1.3(b) subsistence & lodging & Socc 2 Equipment -accommodation?
|
|
1
|
635
|
2 October 2017
|
|
NEC ECC: Option C - Schedule of cost components Item 7
|
|
1
|
670
|
29 September 2017
|
|
NEC ECC: Disallowed, Option A, SSCC for a compensation event
|
|
1
|
618
|
19 July 2017
|