NEC ECC: WAO on Cost of People within a Subcontract
|
|
3
|
781
|
11 January 2019
|
NEC ECC: Under an Option C contract, does the defined cost of "Equipment" include costs associated with repair and maintenance?
|
|
1
|
1486
|
10 January 2019
|
NECECC: Is the provision of a company car, including a fully expensed fuel card allowed under defined cost for an Option C?
|
|
3
|
1453
|
18 December 2018
|
NEC ECC: Option A - People Overheads
|
|
1
|
804
|
23 November 2018
|
NEC ECC: SCC- Item 44
|
|
4
|
1224
|
25 October 2018
|
NEC3 ECC : Should the Project Completion Bonus be paid as part of Defined Cost
|
|
2
|
585
|
10 October 2018
|
NEC ECS: Is travel time payable under option A?
|
|
1
|
701
|
25 September 2018
|
NEC ECC: Working Area Overhead Percentage and Agreed Subcontract Rates
|
|
1
|
3059
|
26 August 2018
|
NEC ECS: What is the definition of a Subsubcontractor under NEC3?
|
|
3
|
1039
|
10 July 2018
|
NEC ECC: Option C - removal of items 12/13 of SCC
|
|
1
|
536
|
7 June 2018
|
NEC ECC: What about maternity pay and also paternity pay?
|
|
3
|
1077
|
6 June 2018
|
NEC ECC: Option C Schedule of Cost Components - People under NEC3
|
|
3
|
1788
|
15 May 2018
|
NEC ECC: Contract Data & SSCC
|
|
3
|
996
|
14 May 2018
|
NEC ECC: Recovering Laundry costs under The Shorter Schedule Of Cost Components
|
|
2
|
488
|
22 March 2018
|
NEC ECC: CECA applied for weekend work when hire cost covered in weekday working?
|
|
1
|
516
|
7 March 2018
|
NEC3 ECC: Option B SSoCC Payments for Electricity
|
|
1
|
527
|
2 March 2018
|
NEC ECC: No working area in SSCC?
|
|
1
|
814
|
1 January 2018
|
NEC3 ECC: Does Defined Cost include the WAOH %
|
|
3
|
742
|
10 November 2017
|
NEC ECC: What about if the Contractor Employs a person who must travel to site, his only working site
|
|
1
|
567
|
9 November 2017
|
NEC3 ECC Option C: Does WAO apply to Agency Supplied Workers?
|
|
3
|
1716
|
3 November 2017
|
NEC ECC: apprenticeship levy a Compensation Event
|
|
3
|
729
|
16 October 2017
|
NEC3 ECC: Option E Fee on Fee
|
|
1
|
2330
|
11 October 2017
|
NEC ECC: What is the difference between Socc 1.3(b) subsistence & lodging & Socc 2 Equipment -accommodation?
|
|
1
|
552
|
2 October 2017
|
NEC ECC: Option C - Schedule of cost components Item 7
|
|
1
|
596
|
29 September 2017
|
NEC ECC: Disallowed, Option A, SSCC for a compensation event
|
|
1
|
575
|
19 July 2017
|
NEC ECC: Option A - Assessment of delay costs - People
|
|
3
|
2522
|
18 July 2017
|
NEC ECC: Option B SSoCC - Travel and Overnight Accommodation Costs
|
|
1
|
1186
|
8 June 2017
|
NEC ECC: Working area SCC People (14)
|
|
2
|
1269
|
5 June 2017
|
NEC ECC: Working Area Overhead Percentages - Inclusions/ exclusions
|
|
1
|
8123
|
21 May 2017
|
NEC ECC: In the contract what is the definition of Defined Costs
|
|
1
|
904
|
12 May 2017
|