Why might the Project Manager not accept the Contractor’s proposal for adding to the Working Areas?
1 Like
If the proposed additional area is either not necessary for Providing the Works or is used for work not in the contract, the Project Manager may not accept the Contractor’s proposal for adding to the Working Areas (see Clause 15.1)