Why is the defects date significant?
It is significant since it triggers payments and ends contractual obligations.
- Following tests and inspections, it is one of two possible dates for making conditional payments.
- It is a deadline for notifying defects which the Contractor is obligated to correct.
- It is one of two possible dates for the supervisor to issue the defects certificate.
- It is a deadline for notifying compensation events.