Why do notifications and communications required by the contract have to be communicated separately?

Why do notifications and communications required by the contract have to be communicated separately?

1 Like

Firstly, because the contract (Clause 13.7) says so. Secondly, the purpose of this is to avoid important matters being overlooked. For example, an early warning notice must be issued separately from a revised programme which shows a delay.