Which people are included in the Schedule of Cost Components?
The SCC identifies two groups of people whose costs costs are included as Defined Cost. They are: people the Contractor directly employs and who nomally work within the Working Areas; and people the Contractor directly employs, who don’t normally work within the Working Areas but are doing so (for example to do unplanned work or work as a result of a compensation event).