Which Party has the responsibility of remedying an ambiguity in the documents?

Which Party has the responsibility of remedying an ambiguity problem or an inconsistency in or between the documents?

1 Like

This is the Project Manager’s responsibility. He should give an instruction which resolves the inconsistency or ambiguity (see Clause 17.1).