Who corrects mistakes in the Bill of Quantities?
The Project Manager corrects mistakes in the Bill of Quantities which are departures from the rules for item descriptions and for division of the work into items in the method of measurement or are due to ambiguities or inconsistencies (see Clause 60.6).