The Project Manager has become aware of an ambiguity in the documents which are part of this contract. What should he do?

The Project Manager has become aware of an ambiguity or inconsistency in or between the documents which are part of this contract. What should he do?

1 Like

As stated in Clause 17.1, on becoming aware of an inconsistency or ambiguity in the documents which are part of the contract, the Project Manager should immediately notify the Contractor.