What should the Project Manager do if he wishes to achieve Completion before the Completion Date?
The Project Manager may instruct the Contractor to submit a quotation for an acceleration to achieve Completion before the Completion Date. The Project Manager states changes to Key Dates to be included in the quotation (see Clause 36.1).