What is the procedure when the Project Manager accepts a quotation for acceleration?

What is the procedure when the Project Manager accepts a quotation for acceleration?

When the Project Manager accepts a quotation for acceleration, he changes the Prices, the Completion Date and the Key Dates accordingly and accepts the revised programme (see Clause 36.3).