When the Project Manager accepts a quotation for acceleration, what does he change?

When the Project Manager accepts a quotation for acceleration, what does he change?

When the Project Manager accepts a quotation for acceleration, he changes the Prices, Key Dates and Completion Date accordingly and accepts the revised programme (see Clause 36.3).