What is the minimum amount of cover or minimum level of indemnity the Contractor has to provide for liability for bodily injury to or death of a person (not an employee of the Contractor) caused by an activity in connection with the contract?
1 Like
The Contractor has to provide insurance cover for the amount stated in the Contract Data for any one event with cross liability so that the insurance applies to the Parties separately (see Clause 84.2 Insurance Table).