Does the Contractor have to provide insurance cover for liability for bodily injury to or death of employees of the Contractor as a result of their employment in connection with the contract?
1 Like
Yes. Liability for death of or bodily injury to employees of the Contractor as a result of their employment in connection with the contract is included in the Insurance Table (see Clause 84.2).