What is a Defect?
1 Like
A part of the works which does not comply with the Works Information,
a part of the works designed by the Contractor which does not satisfy the standard of a relevant law
a part of the works designed by the Contractor which is different from his design which the Project Manager has accepted, or
parts of the works which are not finished or are left out completely (see Clause 11.2(5)).