If the Adjudicator’s decision includes an assessment of additional cost or delay caused to the Contractor, how does the Adjudicator make his assessment?

If the Adjudicator’s decision includes an assessment of additional cost or delay caused to the Contractor, how does the Adjudicator make his assessment?

If the Adjudicator’s decision includes an assessment of additional cost or delay caused to the Contractor, the Adjudicator makes his assessment in the same way as a compensation event is assessed (see Clause W1.3(7)).