The Contractor disputed a Defect notified by the Supervisor. The Adjudicator decided in the Contractor’s favour. What action follows if the Contractor has begun remedial work to correct the Defect?

The Contractor has disputed the existence of a Defect which was notified by the Supervisor and the Adjudicator has decided in the Contractor’s favour. What action should follow if the Contractor has already begun remedial work to correct the Defect?

The Adjudicator would decide on the financial and time effects.