What happens if the Employer does not include within his payment to the Contractor the correct amount of sales tax or VAT?
1 Like
The Contractor should inform the Employer and the Project Manager that his payment does not include the correct amount of VAT/sales tax. The missing amount of sales tax/VAT is then a debt of the Employer.