What happens if the Contractor has not provided the performance bond by the four week fall-back period?

What happens if the Contractor has not provided the performance bond by the four week fall-back period?

Failure to provide the bond within this period entitles the Project Manager to notify the default under Clause 91.2. If the Contractor does not provide the bond within a further four weeks, the Employer is entitled to terminate.