What happens if a guarantee from the Contractor’s parent company is still not provided after the four week fall-back period?

What happens if a guarantee from the Contractor’s parent company is still not provided after the four week fall-back period?

Failure to provide a guarantee within the four week fall-back period entitles the Project Manager to notify of a default under Clause 91.2.