Can the Employer terminate if the Contractor fails to provide a guarantee from his parent company?
If, after four weeks of the Project Manager notifying of a default because of the Contractor’s failure to provide the guarantee, the Contractor still has not provided a guarantee from his parent company, the Employer is entitled to terminate.