What examples of sections would be included under Option X5?
Examples of sections could include the following:
Completion of a major Plant item for commissioning for the Employer’s use ahead of the rest of the works.
Completion of a floor of a multi-storey building so that fitting out by Others can commence.
Completion of a new access route into the Employer’s facilities to enable the existing access route on which part of the works are sited to be closed.