What should the Employer consider when defining sections to be completed earlier than the whole of the works?
When defining sections to be completed earlier than the whole of the works, thought must be given to how the Employer or Others can gaing access to that section. If access is needed through parts of the works that have not yet ben taken over, this will require careful and full explanation in the Works Information.