What should the Project Manager include in his instruction to submit quotations for a compensation event?

What should the Project Manager include in his instruction to submit quotations for a compensation event?

1 Like

The Project Manager should include his decision on whether or not the Contractor gave an early warning which an experienced contractor could have given. This affects the assessment of the event (see Clause 61.5).