I think it depends on whether CECA rates, and relevant % adjustment, are listed within the equipment rates of the SSCC within Contract Data Part Two. If they are then CECA rates shall be applied, if not then you can agree with the Project Manager whether CECA rates or Suppliers invoices can be used to assess defined cost.