This is a compensation event (see Clause 60.1(6)). The Contractor notifies the Project Manager of the event as a compensation event. The obligation to reply within the relevant period is stated in Clause 13.3.
This is a compensation event (see Clause 60.1(6)). The Contractor notifies the Project Manager of the event as a compensation event. The obligation to reply within the relevant period is stated in Clause 13.3.