The Project Manager or Supervisor has changed a decision which he has previously communicated to the Contractor. Is this a compensation event?

The Project Manager or Supervisor has changed a decision which he has previously communicated to the Contractor. Is this a compensation event?

1 Like

This is a compensation event (see Clause 60.1(8)). The Contractor notifies the Project Manager of the event as a compensation event.