The Project Manager or Supervisor has not replied to a communication from the Contractor within the period required by the contract. Is this a compensation event?
1 Like
This is a compensation event (see Clause 60.1(6)). The Contractor notifies the Project Manager of the event as a compensation event. The obligation to reply within the relevant period is stated in Clause 13.3.