The Employer has terminated because he has been released under the law from further performance of the whole of the contract (R17). What is the termination procedure?
1 Like
The Parties follow the procedures outlined in P1 and P3 (Clause 92.1). I.e. the Employer may finish the works and can use any Plant and Materials which he has title to and he can also use Equipment which to which the Contractor has title in order to complete the works. Once the Employer no longer requires this Equipment, he notifies the Contractor and the Contractor removes it promptly.