The Employer has terminated because the Project Manager has given an instruction to stop due to reasons other than a default (R20). What is the termination procedure?

The Employer has terminated because the Project Manager has given an instruction to stop/not start work due to reasons other than the Contractor’s or the Employer’s default and has not given an instruction to re-start within three weeks (R20). What is the termination procedure?

1 Like

The Parties follow the procedures outlined in P1 and P3 (Clause 92.1). I.e. the Employer may finish the works and can use any Plant and Materials which he has title to and he can also use Equipment which to which the Contractor has title in order to complete the works. Once the Employer no longer requires this Equipment, he notifies the Contractor and the Contractor removes it promptly.