The Employer has terminated because an event has occurred which: has stopped the Contractor from completing the works; has stopped the Contractor completing the works by the date shown on the Accepted Programmed and is forecast to delay Completion by more than 13 weeks; neither Party could prevent; and an experienced Contractor would have judged at the Contract Date to have such a small chance of occurring that it would have been unreasonable for him to have allowed for it (R21). What is the termination procedure?
1 Like
The Parties follow the procedures outlined in P1 and P4 (Clause 92.1). I.e. the Employer may finish the works and can use any Plant and Materials which he has title to and the Contractor leaves the Working Areas and removes the Equipment.