Schedule of Cost Components - Parking

NEC4 ECC Option C

A Contractor is submitting invoices for parking costs under the SCC heading of People 13 (a) travel.

Do these parking costs constitute a Defined Cost?

If you are paying for the person who incurred the parking costs under item 11 in the SCC and the travel was a necessary part of Providing the Works then yes, parking costs would be part of item 13(a) travel.