I’ve recently moved jobs where the company is using the NEC4 ECC Option C and E contracts for there framework. Surprisingly they don’t have retention on any work that is undertaken by the Contractor on there framework. I’ve heard there has been situations where the works have been paid by the QS, although works such as post completion surveys haven’t been undertaken, and the PM struggles to get the Contractor back to compete these works.
Is withholding a sum of money for such surveys the only way to get around this on the final valuation? Or is there anything in the contract to to force the Contractor back to undertake the works like post completion surveys even if the final valuation has been paid?