Looking for guidance in the correct method to evaluate a compensation event arising on a project.
Original BofQ identified material to be excavated and deposited into a number of different locations. Each deposition area measured as a separate item within the BQ. No information to check whether this quantity split was correct (other than BQ)
Due to access difficulties, Employer unable to provide access to the intended deposition locations and instead designates all material to go to a new location (further away and much more congested haul) for which no BQ Item exists.
Correct way to evaluate please??
a) Value the operation of taking the material to the new location at defined cost + Fee and create a new BQ Item with all other original items being quantified as zero as the quantity of work undertaken of these items is zero
or
b) Value the cost of the new operation using defined cost + fee and then assess the value of the original operations had they been undertaken at defined cost + Fee to arrive at the change in defined cost arising from the CE. If using this method would you then simply create an additional BQ item as an E.O item and measure the other items as if they had been undertaken or would you just create a whole new single item that equates in value to the original BQ values + the EO cost of the change and then zero the original BQ items.
or
c) as per b) above but create an EO item against each of the original BQ items to assess the increase in defined cost + fee of each changed deposition location
Seems a simple situation, but the mechanics of valuing and then inserting in the BQ seem a bit more complex
Your help would very much be be appreciated