Contractor has increased his commercial team by adding a construction lawyer. Initially the recovery was attempted as a subcontractor but we agree that they are not necessary to provide the works. The Contractor is now looking to recover under people not directly employed, SCC 14 - is this correct?
              
              
              1 Like
            
            
          A lot of lawyers would like to know the answer to this one !
Arguably âYesâ provided certain criteria are met. For instance :
- as they are not normally based within the Working Areas, they would have to be working within the WAs when doing the work;
 - they must not be doing âpreparation for and conduct of an adjudication or proceedings of the tribunalâ as otherwise it will be a Disallowed Cost under the last bullet of clause 11.2 (25). This presents a problem as I am often brought in by a Contractor to provide an independent view on a issue to avoid adjudication or tribunal. However, if my view is that the Contractor has a case, so it is presented to the PM / Employer and they do not then agree with it, it can be slippery slope down to adjudication. When does constructive advice change into preparation for adjudication ?