NEC TERM SERVICE CONTRACT Quotations

We are a contractor working on a term service contract, prior to issuing task orders, the Service Manager has requested we provide quotations for the works prior to issue of the Task Order. There is an additional clause under Payment which states works are to be “re measurable”.

Can the Service Manager re-assess a quote which has previously been accepted and Task order issued if the original forecast is later shown to be wrong? This process will result in us having to pre and re measure the works, essentially doubling workload.

1 Like

@WilliamBrown Would you be able to advise?

Hi Martin, NEC3 or 4? Also, what exactly does the Z clause say?
Basically, upon acceptance of the quotation the Task price is added to the Price List and the Price for Service Provided to Date under the relevant main Option is applied when assessing the amount due.
Happy to discuss further.