Under NEC3 Short Contract when valuing a CE the Contractor has a contract fee of 10% on labour costs but he has subcontracted a specialist who has a contract fee of 15%.
When the Contractor values a CE using in part the subcontractor am I correct in assessing the CE at a Defined Cost of the Subcontractor at his labour cost plus his fee which should then become the Contractors Defined Cost and then add the Contractors Fee?