NEC ECC: The Supervisor is refusing to issue a Defects Certificate due to falling into dispute with the Employer - what can the Contractor do?

sorry, original answer was to a different question!!

One approach could be to engage with the Employer directly and get agreement of what the Defects Certificate would have recorded. The agreement being recorded in accordance with clause 12.3.