The Contractor has submitted a design for a rendered finish to a wall to the PM for acceptance. The WI/scope that the Client provided did not specify the finish required.
The Client has now informed the PM that they may want a masonry clad finish. Is this a CE as the cost is obviously going to be more but the design has not been accepted by the PM yet? It’s an Option C contract.