Hi everyone,
I’m working on an NEC3 Option C project where the contractor has submitted a CE for some additional work we’ve asked him to do.
Originally, it wasn’t clear whether we’d need to do the work at night (as it’s on a busy thoroughfare) or do it during the day.
The contractor included for night work, but actually managed to sort out what we needed within his normal working hours. I accepted the CE as it was for night work (before it transpired that day work was achieved), and the contractor is now claiming that he should be able to claim for the full amount of the CE.
My argument is, “it’s an Option C, I assess the amount due (cl 50.1, 50.2) and your records show it’s been done during the day. You get paid for the work you’ve completed as clause 11.2(29).”
Am I right in this? I appreciate on Option A you pay lump sum, but surely the benefit of Option C is to give me the room to pay for work which is actually completed?
Thanks all.