Under option A, the Works Information contains an instruction to remove and replace all materials across a number of sites but only gives information to the Contractor to quantify the volume of some material and has accidentally omitted around half of the material requirements.
The activity schedule outlines the activities required to complete the works and the prices.
At site it is established that the missing material means the Contractor will be short of material.
It is discovered that the other 50% of material was missing from the WI.
The client thinks the Contractor should have asked before pricing and the price is at the contractor’s risk.
The Contractor thinks the missing information, now being provided, is a change in the Works Information.
What do you think?