NEC ECC: Introduction of new note (parameter) on updated drawing - compensation event or not?)

The issuing of a revised drawing is a compensation event under clause 60.1(1), any additional cost and / or time incurred by the Contractor in relation to what is shown on the revised drawing can be included the compensation event quotation. So if you have to do more design and construction work as a result of the revised drawing you are entitled to recover the cost and time associated.