I am involved with an Option C project where a target programme was set by the Main Contractor which was some 5 weeks shorter than the Contract Programme, we and other subcontractors completed their works within the target programme duration. However one subcontractor did not and as a result we have incurred additional costs in supplying logistics labour and other services which we would not have had to supply had they met the target programme.
Our prices like others were based on everybody buying in to the target programme at tender stage.
Do we have any recourse to claim the additional costs for the five weeks?